Thu, May 7 at 12:58 AM
JSQ-33 via HOB delayed. Dispatch has reported signal failure at CHRS.

Thu, May 7 at 1:34 AM
JSQ-33 via HOB delayed. Maintenance dispatched to investigate signal issue at CHRS.

Thu, May 7 at 1:48 AM
JSQ-33 via HOB 1:55am train cancelled. Next JSQ-33 via HOB train at 2:30am. A signal system issue is being investigated at CHRS.

Thu, May 7 at 2:30 AM
JSQ-33 via HOB delays continue. Signal repairmen are working to resolve a signal problem at CHRS.

Thu, May 7 at 3:31 AM
JSQ-33 via HOB delays continue. Work is ongoing to correct signal failure at CHRS.

Thu, May 7 at 3:45 AM
JSQ-33 via HOB 3:40am train cancelled. Next JSQ-33 via HOB train at 4:15am. Work is ongoing to correct signal failure at CHRS.

Thu, May 7 at 4:19 AM
JSQ-33 via HOB resuming normal service. The earlier signal failure has been resolved at CHRS.