PATH Problems, 06/07/2021

Post Reply
gkazin
Posts: 7617
Joined: Tue Sep 23, 2014 10:05 pm
Location: New Jersey

PATH Problems, 06/07/2021

Post by gkazin »

Sun, Jun 6 at 1:28 PM
PATH Mandatory Hack River Bridge lift for essential marine traffic planned for Mon 6/7 between 5:30am-6am. Please allow extra travel time. We apologize for the inconvenience.
gkazin
Posts: 7617
Joined: Tue Sep 23, 2014 10:05 pm
Location: New Jersey

Re: PATH Problems, 06/07/2021

Post by gkazin »

Mon, Jun 7 at 5:38 AM
NWK-WTC delayed. Scheduled Hackensack River Drawbridge lift in progress. We apologize for the inconvenience.

Mon, Jun 7 at 5:55 AM
NWK-WTC delays continue. Crews working to lock Hack River Draw Bridge. NJT rail is cross honoring PATH passengers at NWK and NYPS.

Mon, Jun 7 at 6:39 AM
While the Hackensack River Drawbridge lift has concluded, NWK-WTC operating with residual delays. NJT rail will discontinue cross honoring PATH passengers at 7am. We apologize for this ongoing inconvenience.

Mon, Jun 7 at 7:02 AM
NWK-WTC resuming normal service. We apologize for the inconvenience this may have caused.