Sat, May 15 at 10:00 PM
Hack River Bridge routine testing planned for tomorrow (Sun 5/16) between 6am-3pm. Please allow extra travel time. We apologize for the inconvenience.
gkazin
Posts: 7617
Joined: Tue Sep 23, 2014 10:05 pm
Location: New Jersey

Re: PATH Problems, 05/16/2021

Post by gkazin »

Sun, May 16 at 11:43 AM
Earlier routine testing on the Hack Bridge is complete. NWK-WTC line continues to operate at slower speeds for single-track operation and may be held at JSQ intermittently. Allow extra travel time. We apologize for the inconvenience.
gkazin
Posts: 7617
Joined: Tue Sep 23, 2014 10:05 pm
Location: New Jersey

Re: PATH Problems, 05/16/2021

Post by gkazin »

Sun, May 16 at 11:07 PM
JSQ-33 via HOB delayed. PAPD responding to a reported incident at HOB. We apologize for the inconvenience.We apologize for the inconvenience.

Sun, May 16 at 11:33 PM
JSQ-33 via HOB delays continue. PAPD continues to investigate an incident at HOB. We apologize for the inconvenience this may have caused.

Mon, May 17 at 12:07 AM
JSQ-33 via HOB resuming normal service. PAPD resolved the earlier investigation at HOB. . . . We apologize for the inconvenience this may have caused. We apologize for the inconvenience this may have caused.