Fri, Jan 7 at 3:00 AM
As of 3:00am, WTC-NWK and JSQ-33 via HOB lines are currently running on or close to schedule. PATH expects to operate normal service throughout the morning commute. We will issue updates as the inclement weather works its way through the area.. Allow extra travel time.
Fri, Jan 7 at 5:00 AM
Good morning! As of 5:00am, WTC-NWK and JSQ-33 via HOB lines are currently running on or close to schedule. PATH expects to operate normal service throughout this morning’s commute. We will issue updates as the inclement weather works its way through the area.
Fri, Jan 7 at 6:00 AM
Hello, PATH riders! WTC-NWK, JSQ-33, HOB-33, and HOB-WTC lines are currently running on or close to schedule. We expect to operate normal weekday service throughout the AM commute. We will issue updates as the inclement weather works its way through the area.
PATH Problems, 01/07/2022
Re: PATH Problems, 01/07/2022
Fri, Jan 7 at 7:16 AM
Hello, PATH riders! As of 7:15am, WTC-NWK, JSQ-33, HOB-33, and HOB-WTC lines continue to run on or close to schedule. We expect to operate normal weekday service throughout the morning commute. We will issue updates as the inclement weather works its way through the area.
Hello, PATH riders! As of 7:15am, WTC-NWK, JSQ-33, HOB-33, and HOB-WTC lines continue to run on or close to schedule. We expect to operate normal weekday service throughout the morning commute. We will issue updates as the inclement weather works its way through the area.
Re: PATH Problems, 01/07/2022
Fri, Jan 7 at 7:44 AM
NWK-WTC, HOB-WTC delayed. Crew investigating reported smoke condition in the track area between EXPL, WTC. JSQ-33, HOB-33 running on or close to schedule. We apologize for the inconvenience.
NWK-WTC, HOB-WTC delayed. Crew investigating reported smoke condition in the track area between EXPL, WTC. JSQ-33, HOB-33 running on or close to schedule. We apologize for the inconvenience.
Re: PATH Problems, 01/07/2022
Fri, Jan 7 at 7:58 AM
PATH suspended. Crew requested 3rd rail power loss due to smoke. NJT rail cross honoring PATH at HOB, NWK, NYPS.
PATH suspended. Crew requested 3rd rail power loss due to smoke. NJT rail cross honoring PATH at HOB, NWK, NYPS.
Re: PATH Problems, 01/07/2022
Fri, Jan 7 at 8:18 AM
PATH remains suspended systemwide. Fire Dept investigating smoke condition. NJT rail and bus cross honoring PATH systemwide. We apologize for the inconvenience.
PATH remains suspended systemwide. Fire Dept investigating smoke condition. NJT rail and bus cross honoring PATH systemwide. We apologize for the inconvenience.
Re: PATH Problems, 01/07/2022
Fri, Jan 7 at 8:29 AM
NWK-JSQ, JSQ-33, HOB-33 resuming with delays. JSQ-WTC and HOB-WTC remains suspended. NJT rail and NJT bus are cross honoring PATH systemwide.
NWK-JSQ, JSQ-33, HOB-33 resuming with delays. JSQ-WTC and HOB-WTC remains suspended. NJT rail and NJT bus are cross honoring PATH systemwide.
Re: PATH Problems, 01/07/2022
Fri, Jan 7 at 9:53 AM
NWK-JSQ & HOB-33 running w/delays. As of 9:50am, JSQ-33 running on 10-min schedule until further notice. JSQ-WTC & HOB-WTC remain suspended. NJT rail & NJT bus are cross-honoring PATH systemwide. NYWW cross-honoring at Hoboken, Paulus Hook, and Brookfield Pl.
Fri, Jan 7 at 10:50 AM
PATH resuming normal service. Earlier smoke condition resulting in 3rd rail power loss has concluded between EXPL, WTC. NJT rail and bus are cross honoring PATH at HOB, NWK, NYPS. NYWW no longer cross honoring PATH at 11:00 am. We apologize for the inconvenience this may have caused.
Fri, Jan 7 at 1:45 PM
Friday, 1/7/22, PATH will operate supplemental svc on the JSQ-33 via HOB line. Extra trains depart JSQ at 10:45p, 11:15p and 33rd at 11:20p, 11:50p. This service modification was put in place to alleviate crowding. We encourage you to stay safe and continue to #MaskUp.
NWK-JSQ & HOB-33 running w/delays. As of 9:50am, JSQ-33 running on 10-min schedule until further notice. JSQ-WTC & HOB-WTC remain suspended. NJT rail & NJT bus are cross-honoring PATH systemwide. NYWW cross-honoring at Hoboken, Paulus Hook, and Brookfield Pl.
Fri, Jan 7 at 10:50 AM
PATH resuming normal service. Earlier smoke condition resulting in 3rd rail power loss has concluded between EXPL, WTC. NJT rail and bus are cross honoring PATH at HOB, NWK, NYPS. NYWW no longer cross honoring PATH at 11:00 am. We apologize for the inconvenience this may have caused.
Fri, Jan 7 at 1:45 PM
Friday, 1/7/22, PATH will operate supplemental svc on the JSQ-33 via HOB line. Extra trains depart JSQ at 10:45p, 11:15p and 33rd at 11:20p, 11:50p. This service modification was put in place to alleviate crowding. We encourage you to stay safe and continue to #MaskUp.