Mandatory Hack River Bridge lifts scheduled Sun 01-08-2023:
1st lift: 8:00am-9:00am
2nd lift: 11:00am-12:00pm
Times are subject to change.

Sun, Jan 8 at 4:07 PM
JSQ-33 via HOB delayed. Crew reported air brake problem at JSQ. We apologize for the inconvenience.

Sun, Jan 8 at 4:48 PM
JSQ-33 via HOB delays continue. Crew is investigating the train with an air brake problem at JSQ.

Sun, Jan 8 at 5:35 PM
JSQ-33 via HOB delays continue. Crew is working on the train with an air brake problem at JSQ.

Sun, Jan 8 at 6:35 PM
JSQ-33 via HOB resuming normal service. Crew resolved the earlier air brake problem at JSQ. We apologize for the inconvenience this may have caused.

Mon, Jan 9 at 4:21 PM
NWK-WTC delayed. Crew reported mechanical problems on a train between JSQ, HAR. We apologize for the inconvenience.

Mon, Jan 9 at 4:48 PM
NWK-WTC resuming normal service. Crew resolved the earlier mechanical problem between HAR, JSQ. We apologize for the inconvenience this may have caused.

Mon, Jan 9 at 5:29 PM
JSQ-33, HOB-33 delayed. Crew reported complaint of a disruptive passenger on a train at 9th St. We apologize for the inconvenience.

Mon, Jan 9 at 5:56 PM
JSQ-33 resuming normal service. HOB-33 remains delayed. PAPD removed a disruptive passenger from a train at 9th St.

Mon, Jan 9 at 6:12 PM
HOB-33 resuming normal service. The earlier incident with a disruptive passenger has been resolved at 9th St. We apologize for the inconvenience this may have caused.