Thu, Jan 12 at 7:00 AM
Mandatory Hack River Bridge lifts scheduled Thu 01-12-2023:
1st lift: 10:00am-11:00am
2nd lift: 1:00pm-2:00pm

Thu, Jan 12 at 9:09 AM
NWK-WTC may experience delays. Mandatory FRA signal testing will be taking place on the Amtrak Dock Bridge between 10am-2pm. We apologize for the inconvenience.

Thu, Jan 12 at 9:57 AM
JSQ-33 delayed. Crew reported mechanical problems on a train at JSQ. We apologize for the inconvenience.

Thu, Jan 12 at 10:24 AM
JSQ-33 resuming normal service. Crew resolved the earlier mechanical problem at JSQ. We apologize for the inconvenience this may have caused.

Thu, Jan 12 at 2:41 PM
HOB-33 delayed. Crew reported mechanical problems on a train at 33rd St. We apologize for the inconvenience.

Thu, Jan 12 at 3:07 PM
HOB-33 resuming normal service. Crew resolved the earlier mechanical problem at 33rd St. We apologize for the inconvenience this may have caused.