PATH Problems, 02/16/2023

Post Reply
gkazin
Posts: 7617
Joined: Tue Sep 23, 2014 10:05 pm
Location: New Jersey

PATH Problems, 02/16/2023

Post by gkazin »

Mandatory Hack River Bridge lifts scheduled Thu 02-16-2023:
1st lift: 10:00am-11:00am
2nd lift: 1:00pm-2:00pm
Times are subject to change.

Thu, Feb 16 at 7:19 AM
HOB-WTC delayed. Crew reported mechanical problems on a train at WTC.

Thu, Feb 16 at 7:52 AM
HOB-WTC delays continue. Crew working to resolve a train with a mechanical problem at WTC.

Thu, Feb 16 at 8:04 AM
HOB-WTC resuming normal service. Crew resolved the earlier mechanical problem at WTC.

Thu, Feb 16 at 12:18 PM
NWK-WTC delayed. Crews preparing for track maintenance between HAR, JSQ.

Thu, Feb 16 at 12:49 PM
NWK-WTC resuming normal service. Track maintenance has concluded between HAR, JSQ.
Post Reply