PATH Problems, 05/27/2023
Posted: Sat May 27, 2023 2:08 pm
Sat, May 27 at 1:22 PM
JSQ-33 via HOB delayed. Crew reported track circuit failure at JSQ. Trains may operate at slower speeds.
Sat, May 27 at 1:39 PM
JSQ-33 via HOB delays continue. Crews investigating a track circuit failure at JSQ.
Sat, May 27 at 1:53 PM
JSQ-33 via HOB delayed. Crews working to resolve track circuit failure at JSQ.
Sat, May 27 at 2:21 PM
JSQ-33 via HOB resuming normal service. Crews repaired the earlier track circuit failure at JSQ.
JSQ-33 via HOB delayed. Crew reported track circuit failure at JSQ. Trains may operate at slower speeds.
Sat, May 27 at 1:39 PM
JSQ-33 via HOB delays continue. Crews investigating a track circuit failure at JSQ.
Sat, May 27 at 1:53 PM
JSQ-33 via HOB delayed. Crews working to resolve track circuit failure at JSQ.
Sat, May 27 at 2:21 PM
JSQ-33 via HOB resuming normal service. Crews repaired the earlier track circuit failure at JSQ.